Object

Proposed Submission Core Strategy and Policies Development Plan Document Review

Representation ID: 5404

Received: 03/03/2015

Respondent: Northern Fringe Protection Group

Number of people: 323

Legally compliant? Not specified

Sound? No

Duty to co-operate? Not specified

Representation Summary:

The Core Strategy fails to take sufficient account of the waste water issues arising from proposed expansion of Ipswich. The Draft Strategic Economic Plan identified the scale and cost of new connections as inhibiting development of some strategic sites. The Water Cycle Study shows that significant upgrading is required to wastewater treatment capacity. The pipeline from north Ipswich to Cliff Quay is at capacity and no viable solutions for the Garden Suburb have been proposed. This could seriously undermine the delivery of the Core Strategy.

Full text:

See attachment

Object

Proposed Submission Core Strategy and Policies Development Plan Document Review

Representation ID: 5700

Received: 05/03/2015

Respondent: Save Our Country Spaces

Legally compliant? No

Sound? No

Duty to co-operate? No

Representation Summary:

SOCS endorse the NFPG's points. The Core Strategy fails to take sufficient account of the waste water issues arising from proposed expansion of Ipswich. The Draft Strategic Economic Plan identified the scale and cost of new connections as inhibiting development of some strategic sites. The Water Cycle Study shows that significant upgrading is required to wastewater treatment capacity. The pipeline from north Ipswich to Cliff Quay is at capacity and no viable solutions for the Garden Suburb have been proposed. This could seriously undermine the delivery of the Core Strategy.