Object
Proposed Submission Core Strategy and Policies Development Plan Document Review
Representation ID: 5404
Received: 03/03/2015
Respondent: Northern Fringe Protection Group
Number of people: 323
Legally compliant? Not specified
Sound? No
Duty to co-operate? Not specified
Representation Summary:
The Core Strategy fails to take sufficient account of the waste water issues arising from proposed expansion of Ipswich. The Draft Strategic Economic Plan identified the scale and cost of new connections as inhibiting development of some strategic sites. The Water Cycle Study shows that significant upgrading is required to wastewater treatment capacity. The pipeline from north Ipswich to Cliff Quay is at capacity and no viable solutions for the Garden Suburb have been proposed. This could seriously undermine the delivery of the Core Strategy.
Full text:
See attachment